某涉外项目-(中英双语版)-现场电气设备安装及调试方案

某涉外项目-(中英双语版)-现场电气设备安装及调试方案 本文关键词:涉外,中英,设备安装,调试,电气

某涉外项目-(中英双语版)-现场电气设备安装及调试方案 本文简介:SPCⅡ现场电气设备安装及调试方案SPCⅡElectricEquipmentFieldInstallationandCommissioningmethodstatement版本Rev.编制Preparedby审核Reviewedby批准Approvedby认可Acceptedby目录1.目的2pur

某涉外项目-(中英双语版)-现场电气设备安装及调试方案 本文内容:

SPCⅡ现场电气设备安装及调试方案

SPCⅡ

Electric

Equipment

Field

Installation

and

Commissioning

method

statement

版本Rev.

编制Prepared

by

审核Reviewed

by

批准Approved

by

认可Accepted

by

1.目的2

purpose2

2.工作范围2

work

scope2

3.编制依据2

references2

4.施工准备2

Preparation

for

construction2

4.1工机具准备2

Preparation

for

machine

and

tools2

4.2应配备下列人员:3

Preparation

for

personnel3

4.3技术准备3

Preparation

for

technical3

4.4材料准备3

Preparation

for

materials3

4.5人员准备3

Preparation

for

construction

person3

5.电气设备安装要求4

installation

requirment4

6.金属构件制作安装及控制箱、盒安装5

metal

component

fabrication

and

installation,control

box

installation5

6.1操作柱的制作安装5

operation

post

fabrication5

7.电动机检查6

electromotor

inspection6

7.1作业条件6

work

condition6

7.2作业方法6

work

method6

7.3电动机启动调试7

start

commissioning7

8.照明安装。12

Illumination

installation12

8.1导线的敷设12

lead

pulling12

8.2照明灯具作业方法和步骤12

lighting

appliance

working

method

and

steps12

9.交工验收要求12

handover

acceptance

requirements12

10.危险点分析13

hazardous

analysis13

1.

目的

purpose

本程序描述拜耳聚碳酸酯SPCII项目电气设备安装有关规定。为保证电气设备的正确安装及电动机能安全投入运行,促进施工管理和技术水平的提高。

This

procedure

describes

the

related

provision

on

electrical

equipment

installation

of

Bayer

Polymers

SPCII

project

so

as

to

ensure

the

correct

installation,operation

and

promote

the

administration

and

technology

skills.

2.

工作范围

work

scope

适用于拜耳聚碳酸酯SPCII项目,主要区域为B204、B244、B209;其中电机就地控制按钮共计51个;就地控制盘2个;电机就地控制转换开关54个;电动机检查及启动调试共计68台;照明安装

28盏。

It

is

applied

to

the

main

area

B204、B244、B209

of

Bayer

Polymers

SPCII

project,among

which

there

are

51

electrical

grounding

control

button;

2

grounding

control

panel;54electrical

grounding

control

switch;

68

motor

inspection

and

commissioning

and

28

lighting

installation.

3.

编制依据

references

·GBJ

50254-96

电气安装工程低压电器施工及验收规范;

LV

electrical

apparatus

construction

and

acceptance

code

for

electrical

installation

engineering

GBJ

50254-96

·GBJ

50255-96

电气安装工程电力变流设备施工及验收规范;

Electric

power

variable

current

equipment

construction

and

acceptance

code

for

electrical

installation

engineering

GBJ

50255-96

·GBJ

50256-96

电气安装工程起重机电气装置施工及验收规范;

Lifting

electric

device

construction

and

acceptance

code

for

electrical

installation

engineering

GBJ

50256-96

·GBJ

50257-96

电气安装工程爆炸和火灾危险环境电气装置施工及验收规范;

Electrical

equipment

construction

and

acceptance

code

in

explosive

and

fire

enviroment

for

electrical

installation

engineering

GBJ

50257-96

·GBJ

50303-2002

建筑电气工程施工质量验收规范;

Code

for

construction

and

acceptance

of

electrical

engineering

GBJ

50303-2002

4.

施工准备

Preparation

for

construction

4.1

工机具准备

Preparation

for

machine

and

tools

电锤、手锤、电缆剪断钳、兆欧表、万用表、钳型电流表、切割机、磁力线坠、斜口钳、机械和液压工具、力矩扳手、电工刀。

Electric

hammer,hand

hammer,cable

cutting

pliers,megohmmeter,multimeter,clamp-type

ammeter,cutting

machine,magnetic

line

cone,inclined

mouth

pliers,mechanical

and

hydraulic

pressure

tools,moment

spanner,electrician’s

knife.

4.2

应配备下列人员:

Preparation

for

personnel

安全监督员、施工队长、班长、取得施工资格的工人。

Safety

officer,construction

team

leader,foreman,qualified

certificate

worker.

4.3

技术准备

Preparation

for

technical

4.3.1

熟悉电机安装位置。

Familiarize

with

installation

location

4.3.2

核对电机及电缆规格、型号与电缆清册相符

Check

the

specification

and

model

of

motor

and

cable

against

cable

checklist.

4.3.3

熟悉照明灯具的具体安装位置,电源电缆的敷设路径及端接位置。

Familiarize

with

the

concrete

installation

location

of

lighting

device,layout

route

of

power

cable

and

termination

place.

4.3.4

核对图纸和清册,并与相关专业进行图纸会审。

Checking

drawing

and

cable

list,making

a

joint

drawing

check

up

with

relevant

professional.

4.4

材料准备

Preparation

for

materials

C型钢、槽钢、膨胀螺栓、螺栓等。

C

steel,channel

steel,expansion

bolt,bolt

and

so

on.

4.5

人员准备

Preparation

for

construction

person

序号

No.

职务

title

姓名

Name

责任

Duty

1

施工队长

Construction

team

leader

宋建平

Song

jianping

全面负责电气设备安装

In

for

charge

of

E

job

slip

and

work

permit

will

be

needed

when

working

in

the

production

area.

It

is

forbidden

to

work

if

no

work

permits.

3.

进入B204一期生产区作业施工时,该生产区域内介质都为有毒的液体、气体或粉末状物质,应在施工区域内拉上警戒线,并搭设防护栏;在规定的警戒线范围内施工。

Guard

line

and

safety

rail

will

be

established

and

work

in

the

stated

range

when

construction

can

be

done

in

first

term

of

B204

area

because

this

area

is

poisonous.

4.

施工用电严禁将电线直接勾挂在闸刀上或直接插入插座内使用。

It’s

forbidden

to

directly

hang

the

wire

of

construction

electricity

on

the

brake

or

plug

into

receptacle

for

usage.

5.

电源线路不得接近热源或直接绑挂在金属构件上。

Wiring

route

of

power

supply

should

not

be

clost

to

heat

source

or

directly

tie

with

the

metal

components.

6.

在光线不足及夜间工作的场所应有足够的照明,主要通道上应装设路灯。

There

should

be

enough

illumination

for

places

without

sufficient

lighting

or

night

working

area,and

road

lamp

standing

on

the

main

routeway

7.

进入施工现场请带好安全帽,上高必须系安全带。使用梯子需有人监护,梯子底部应有防滑措施,人字梯需有限制张开的绳索,且一张梯子上不得站两人。

Wear

safety

helmet

prior

to

entering

construction

site

and

tie

safety

belt

when

climbing

upwards.

It

demands

guardians

and

slide-proof

measures

at

the

bottom

when

using

ladder.

trestle

type

ladder

should

be

equiped

with

rope

which

restricts

spread.

and

just

one

person

one

ladder.

8.

使用电动工具和电火焊器械必须按规程操作。

operating

electromotor

tools

and

electrical,fire,welding

instrument

according

to

regulations.

9.

施工场所每天应清理整顿,做到工完料尽场地清。

Clean

up

the

construction

site

everyday

to

catch

the

saying

that

when

the

work

finished

the

materials

are

used

up

and

site

clean.

10.

运输设备时,注意设备和人身安全,不要损坏设备的油漆,内部元件以及其表面的平整度。

During

transit,maintain

both

equipment

and

personnel

safely

and

donot

destroy

the

paint,inner

element

and

the

surface

level

of

equipment.

11.

所有作业人员应严格执行《电业安全工作规程》中的有关规定。

All

workers

should

strictly

observe

and

follow

the

provisions

in

safety

construction

codes

of

electrical

industry

12.

电机试运时,应定时巡视,确保设备及人身安全。

When

motor

trial

operation,carry

out

regular

patrol

to

ensure

equipment

and

personnel

safety

13.

送电操作时,双方应取得联系,严格执行操作监护制度

When

power-on

operation,carry

out

mutual

communication

and

strictly

implement

operation

guardianship

system.

20